Key findings
- Consensus was reached that 132kV operating voltage is the cost-optimal next array voltage, with 132kV offering significant cost savings over 66kV, even for wind turbines of 14MW, which are currently available at 66kV.
- The study found that that the earliest 132kV wind farms could be operational is the end of the 2020s, even with immediate proactive work from developers and the supply chain. This highlights the urgency with which the industry must move to make the transition to 132kV operating voltage.
- Further work was identified to accelerate the transition to 132kV. This includes defining robust requirements and standards for 132kV cables; development, qualification and testing of 132kV cables; understanding the implications of 132kV on floating wind; and developing improved cable connectors and testing methods.
About the project
The project partners are: Carbon Trust, EnBW, Equinor, Ocean Winds, Ørsted, RWE, ScottishPower Renewables, Shell, SSE Renewables, TotalEnergies and Vattenfall.
TNEI and Petrofac delivered the OWA High Voltage Array Systems project, working closely with the Carbon Trust and the project partners. They also received inputs from Hellenic Cables and Orient Cable who were contracted to develop concept designs for various high voltage array cables. All delivery contractors were identified through competitive tender processes. During the project, TNEI and Petrofac also engaged numerous technology manufacturers, array system installers, system operators, regulators, universities, and research institutions.